Construction

1. Clear vegetation where required
2. Level and flatten ground where required
3. Build supporting wall to hold up ground where required (bit like current sitting area)
4. Plant grass where required (might be bare after leveling ground)
5. Potentially plant trees for future shade
……………………………………………………………………………………………………………


Works and construction sequence:
1. Clean and clear out house
2. Repair roof (if required), ceiling, door, and window
3. Build internal partition walls
4. Paint internal walls and ceilings (white lime paint)
5. Seal earth floor with stone tiles or concrete
6. Seal any other openings to stop animals getting in
7. Build cupboards and storage system out of timber
……………………………………………………………………………………………………………


Works and construction sequence:
1. Construct work area housing ovens, grills and stoves (stone)
2. Construct support structure for roof (timber)
3. Construct roof (terracotta tiles or green roof)
4. Lay down stone floor tiles around work area

……………………………………………………………………………………………………………


Works and construction sequence:
1. Construct work area seats and table (stone/timber)
2. Construct support structure for roof (timber)
3. Construct roof (timber) May use sail for shading in the beginning
4. Lay down stone floor tiles around work area
……………………………………………………………………………………………………………


Works and construction sequence:
1. Install water line from water source (coordinate with ground leveling)
2. Build fountain structure with tap (stone/concrete)
3. Build sinks and trough


Prepare landscape



Storage house (Baba M small house)



Cooking area



Food preparation/serving area



Water area



Start